FREQUENTLY ASKED QUESTIONS
About ground-mounted solar and EPC.
Frequently asked questions about services, project preparation, installation and maintenance.
30 questions
What projects does YDK Mühendislik focus on?
Our main focus is turnkey ground-mounted solar plants for investors and corporate clients. We deliver engineering, procurement and site execution within the EPC scope.
Explore our EPC scopeAre electrical, mechanical and perimeter fencing works included?
Yes. Our services extend from design and procurement through earthworks, site preparation, mechanical and electrical installation, transformers and MV connections to fencing, CCTV, commissioning, acceptance and maintenance. Included items are defined by the technical specification and contract.
What information is needed for the first discussion?
Site location and land parcel details, target capacity, the current project stage and any available connection or permit documents are enough to begin the initial assessment.
Project preparation guideHow long does a ground-mounted solar project take?
The programme depends on capacity, site conditions, equipment availability and relevant approvals. A project-specific schedule is prepared following the site survey and technical assessment.
Do you provide maintenance after installation?
We provide regular maintenance, module cleaning and system performance assessment. The scope is defined according to the plant's needs and equipment requirements.
Commissioning and maintenanceHow can I contact YDK Mühendislik?
Contact our Ceyhan / Adana team on +90 534 506 83 86 or at info@ydkmuhendislik.com.
Contact detailsHow does turnkey ground-mounted solar differ from installation-only services?
Installation-only services cover defined site works using specified equipment and designs. Turnkey EPC combines engineering, procurement and construction. The proposal and contract should still explicitly define which permitting, connection, testing and maintenance activities are included.
Turnkey Ground-Mounted SolarWhat information determines the cost of ground-mounted solar installation?
Alongside capacity, the assessment considers ground conditions and slope, site access, equipment selection, electrical connection scope and ancillary infrastructure. A price stated only per MW does not mean all of these works are included on the same basis.
Turnkey Ground-Mounted SolarHow should I prepare for an initial EPC discussion with YDK?
Share the location and land parcel details, target capacity and available layout and connection documents. Distinguishing completed documentation from outstanding steps allows technical assessment and construction planning to start from the correct project stage.
Turnkey Ground-Mounted SolarDo you also undertake transformers and MV connections?
Yes. Transformers and medium-voltage connections are within our service offering. Equipment procurement, site works and responsibilities at the connection point are defined using the project documents.
Electrical Infrastructure and ConnectionsWhich documents are needed for electrical infrastructure?
Existing electrical drawings, the layout, connection information and an equipment list support the assessment. Missing documents or those awaiting revision should also be identified at the outset.
Electrical Infrastructure and ConnectionsCan electrical works be planned before mechanical installation is complete?
Planning should be coordinated. Inverter positions, cable routes and module arrays influence each other. The construction sequence is then determined by the approved design, access and workplace safety conditions.
Electrical Infrastructure and ConnectionsCan solar modules be installed on sloping terrain?
Suitability cannot be determined from slope alone. Ground conditions, topography, mounting-system design and access must be reviewed together. The installation method follows a project-specific technical assessment.
Mechanical and Module InstallationAre mounting structures and module installation considered together?
Yes. Structures, module placement and mechanical connections are planned as a coordinated package. Procurement and installation responsibilities are clarified alongside the technical documents for the selected system.
Mechanical and Module InstallationWhat should a mechanical installation proposal specify?
It should document the mounting system and modules, foundation works, material responsibilities, site conditions, inspection and handover expectations. Comparing module counts alone does not establish scope boundaries.
Mechanical and Module InstallationIs site preparation included in turnkey delivery?
We undertake earthworks, site preparation and ancillary infrastructure. Quantities, boundaries, roads and any drainage requirements are established through technical review and written into the project scope.
Site Preparation and InfrastructureAre site photographs sufficient for a firm proposal?
Photographs support an initial discussion but do not replace information about levels, ground conditions and access. A firm scope requires the available surveys and designs together with the necessary site assessment.
Site Preparation and InfrastructureAre service roads planned only for construction?
No. Material deliveries and installation access are considered alongside operation, fault response and maintenance access. Roads are assessed together with the module layout and other infrastructure.
Site Preparation and InfrastructureDo you undertake fencing, access gates and CCTV together?
Yes. Perimeter fencing, entrance and service gates and CCTV infrastructure are within our services. Routes, equipment and connection needs are defined by the site design.
Perimeter Fencing and Site SecurityIs a price per metre sufficient to compare fencing proposals?
No. Material specifications, foundations and connections, gates, terrain slope and scope boundaries should be compared on the same basis. Length alone does not define the completed work.
Perimeter Fencing and Site SecurityWhat information is needed to plan CCTV?
Share the site layout, entrance points, existing power and communications infrastructure and monitoring requirements. Equipment and installation are technically assessed using these inputs.
Perimeter Fencing and Site SecurityIs solar maintenance only module cleaning?
No. Cleaning can be one part of maintenance. Equipment, connections, site conditions, monitoring and fault records are also assessed. Checks are defined according to the needs of the plant.
Commissioning and MaintenanceCan you specify a fixed maintenance interval?
One interval cannot be assumed suitable for every plant. A plan is developed using manufacturer requirements, site conditions and operating records. Suspected faults or safety concerns should be referred to qualified technical personnel without waiting for routine maintenance.
Commissioning and MaintenanceWhich records should I bring to a maintenance discussion?
Share the equipment list and project documents, generation and alarm records, previous maintenance reports and dates of the observed issue. These inputs help define the scope of the site assessment.
Commissioning and MaintenanceHow much land does a ground-mounted solar plant need?
Capacity alone is not enough to determine this. Modules and mounting systems, slope, row arrangement, roads and technical areas influence the layout. A firm land requirement should not be given without reviewing parcel and design data.
Initial Assessment for a Ground-Mounted Solar ProjectCan I contact YDK before having a completed design?
Yes. Start by sharing available information and identifying missing documents. Design, procurement and construction needs are assessed separately; an initial discussion does not replace a suitability assessment or approval.
Initial Assessment for a Ground-Mounted Solar ProjectIs the lowest price per MW the best EPC proposal?
Not by itself. Compare the same capacity, equipment and included work. Infrastructure, connections or handover activities purchased separately change the total project budget.
Understanding the Scope of a Turnkey EPC ProposalDoes turnkey automatically mean that every activity is included?
The proposal, technical specification and contract establish the boundaries. Site preparation, electrical connections, acceptance, documentation and maintenance should be explicitly listed with their responsible parties.
Understanding the Scope of a Turnkey EPC ProposalDoes lower generation automatically mean the modules need cleaning?
No. Weather, monitoring data, alarms and equipment condition should be considered together. Cleaning or another intervention is determined after observation and technical assessment.
Planning Maintenance for a Ground-Mounted Solar PlantWhat should I include in an initial maintenance enquiry?
State the plant location, capacity, equipment, last maintenance date and whether you need planned maintenance or help with an observed issue. Prepare relevant alarm and generation records with their dates where available.
Planning Maintenance for a Ground-Mounted Solar PlantLET'S DISCUSS YOUR PROJECT
Start with your requirements.
Let's define the technical scope and delivery roadmap for your ground-mounted solar project together.
