Review each work package
Compare the scope of electrical, mechanical, site infrastructure, fencing and commissioning work. An item included in one proposal may remain the client's responsibility in another.
Match equipment with technical documents
Check that module, inverter and mounting system makes and models align with the technical specification. Clarify warranty and installation obligations separately.
Define connection and site boundaries
Responsibilities for plant works, the connection point, transformer and switchgear requirements, roads and ancillary infrastructure should be recorded in writing.
Define handover
Establish testing, documentation, commissioning and subsequent support at the outset. Distinguish estimated generation from contractual guarantees.
Compare two EPC proposals on an equal basis
First check whether both proposals describe the same capacity, layout, equipment and scope. Comparing totals is misleading if one excludes site preparation or transformer connections. Identify procurement, installation, inspection and handover responsibility for every work package. Ask for ambiguous terms to be clarified in a revised proposal rather than relying on verbal explanations.
Changes, warranties and maintenance boundaries
Site conditions or design revisions can change quantities. Discuss in advance how scope and programme changes will be handled. Manufacturer warranties, installation responsibility and maintenance services are different matters. Define who to contact for faults, what site interventions include and how long post-handover services last. An estimated energy yield should not be read as an unconditional production commitment.
Is the lowest price per MW the best EPC proposal?
Not by itself. Compare the same capacity, equipment and included work. Infrastructure, connections or handover activities purchased separately change the total project budget.
Does turnkey automatically mean that every activity is included?
The proposal, technical specification and contract establish the boundaries. Site preparation, electrical connections, acceptance, documentation and maintenance should be explicitly listed with their responsible parties.
Pre-discussion checklist
- Included and excluded works
- Technical specification and equipment list
- Electrical and connection boundaries
- Civil works and perimeter fencing
- Testing, handover and warranty scope
This guide provides preliminary information. Final system selection, execution scope and technical suitability depend on a site survey and project assessment.